09/06/2026
🌍 HORNINGSEA PARK 🌍
‼️ Raft Waffle Pod Slab – Two Storey Dwelling Construction Update ‼️
Construction is progressing well on our new two-storey residential dwelling, with the team currently completing the ground floor raft waffle pod slab. Reinforcement placement, beam cages, and formwork are now being finalised in preparation for the concrete pour.
Our structural engineers have been on site undertaking detailed inspections of all reinforcement, including edge beams, internal beams, step-downs, slab thickenings, and critical load-bearing elements throughout the slab system.
Particular attention has been given to areas over bored piers and waffle pod cut-outs, which are being filled with mass concrete to accommodate increased structural loads and ensure compliance with the engineering design.
These inspections verify that all reinforcement has been installed correctly, specified concrete cover requirements are achieved, and the slab is fully prepared for a successful pour.
Another major milestone delivered smoothly through strong collaboration between the builder, contractor, and engineering team. We look forward to seeing the slab poured and progressing to the next stage of construction. 🏗️